Which of the following should a project manager consult when deciding how to send updates regarding deliverables?
Correct : D
A communication plan details the communication requirements, including methods, frequency, and stakeholders for each type of update. According to CompTIA Project+, this plan is essential for ensuring effective and organized communication throughout the project.
Start a Discussions
Which of the following cloud models can be used to speed up the development of a service that integrates with the operating system and accelerates the delivery of a software project?
Correct : D
PaaS (Platform as a Service) provides a platform allowing developers to build and deploy applications quickly. It offers development tools and integrations with the operating system, which speeds up development and delivery. This model is highlighted in CompTIA Project+ as ideal for software development environments.
Start a Discussions
A project sponsor requires a system that is capable of providing integrated management of all the business's core functions. Which of the following systems is the project sponsor describing?
Correct : D
ERP (Enterprise Resource Planning) systems are designed to integrate and manage all core functions of a business, such as finance, HR, and supply chain management. This aligns with CompTIA Project+ guidelines on selecting appropriate systems for organizational needs.
Start a Discussions
Which of the following contract types would be most beneficial to both parties in cases in which the scope of the project has a large number of unknowns?
Correct : D
Time and materials contracts are flexible and beneficial when the project scope has many unknowns. They allow costs to be adjusted based on actual time and resources used, which is consistent with CompTIA Project+ recommendations for projects with uncertain requirements.
Start a Discussions
Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?
Correct : B
A Sprint Review involves reviewing the completed backlog items and presenting the work to stakeholders. This aligns with CompTIA Project+ agile practices, where a Sprint Review focuses on completed tasks and feedback.
Start a Discussions
Total 291 questions