Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
Using the Project Scenario and Marketing Additional information, answer the following question:
Which approach BEST outlines how to apply the 'continued business justification' principle during the initiation stage?
Correct : B
Continued business justification ensures that the project remains viable throughout its life cycle. By confirming that funding is available, the project manager ensures that there are sufficient resources to support the project, aligning with the principle of maintaining justification for the project's continuation.
Start a Discussions
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Staff Training - Additional information
The event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:
A . the event is carried out safely and professionally;
B . staff members are able to give advice on health and fitness.
This is covered by four work packages:
1. Training syllabus:
* High-level design of the manual.
* Content of each module.
2. Course content for safety and professionalism:
* Detailed design of two modules:
* Health and Safety including basic first aid.
* Customer relations to look after people attending the event.
* Piloting the modules with a group of volunteers.
3. Course content tor giving advice on health and fitness:
* Detailed design of two modules:
* Exercise fundamentals including how to warm up and cool down.
* Healthy eating including what types of food are good for you.
* Piloting the modules with a group of volunteers.
4. Training delivery:
* Production of the training manual;
* Delivery of the training to the rest of the volunteers.
The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.
Using the Project Scenario and Staff Training Additional information, answer the following question:
The Staff Training Team has developed the following user stories:
* 'As a volunteer, I want to be trained in healthy eating so that I can answer questions from the public on the long term aims of the LGA during the football tournament.' - Should Have
* As the LGA. I want all volunteers to have received mandatory health and safety training so that we can ensure that the event takes place in a safe environment for the public.' - Must Have
A suitably qualified trainer has been scheduled to deliver a course covering both requirements. Unfortunately, there is no-one available from the LGA to quality check the course materials for the healthy eating training until three days after the date scheduled for training delivery.
How should the team respond to this situation?
Correct : B
Rescheduling the training delivery ensures that the volunteers receive the necessary and quality-checked materials for healthy eating, which is important for providing accurate information to the public. This approach maintains the integrity of the training while still addressing the mandatory health and safety training requirement. It prevents the risk of delivering potentially inadequate or unchecked content.
Start a Discussions
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Marketing - Additional information
The marketing campaign has two key areas to promote:
1. The event itself including the football tournament, event village and fundraising activities.
2. The LGA's long term aim to improve the fitness of children under the age of 16.
The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.
The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.
They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.
The Marketing Team is not clear on the priority to assign to the two aims for the event.
The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.
Nine releases are scheduled at the end of each of the nine week-long timeboxes.
The nine timeboxes within the marketing work stream are scheduled to include:
Using the Project Scenario and Marketing Additional Information, answer the following question:
For which marketing product would a quality method of automated test-driven development be MOST suited?
Correct : C
Automated test-driven development (TDD) is particularly well-suited for digital products like website content, where code and links can be continuously tested for functionality and correctness. This approach allows for rapid iterations and ensures that updates do not introduce errors, making it ideal for maintaining the quality of web content.
Start a Discussions
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Website - Additional information
A new website will be built for the event. There are five work packages within this product:
1. Initial homepage:
2. Team Registration functionality:
3. Social media promoting the event and its aims.
4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.
5. Health Park:
The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.
The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.
Using the Project Scenario and Website Additional information, answer the following question:
During the 'initiating a project' process, the project manager has decided to use the Cynefin framework to assess the project.
As a result, the following observation was made as part of the assessment:
'There is a relationship between the social media websites promoting active lifestyles and participation in sport. This in turn leads to an increase in the health and fitness of the people.
It will not be possible to measure the effect of the social media websites until after the project. The results of early communications on the websites should be reviewed in order to identify what effect it may be having, and why. This will then feed into further longer term initiatives at the LGA.'
How should this relationship be assessed according to the Cynefin framework?
Correct : C
In the complex domain, cause-and-effect relationships are not immediately apparent and can only be understood in retrospect. The relationship between social media websites promoting active lifestyles and their effect on health and fitness is not straightforward, as it involves multiple interacting factors. Since it will not be possible to measure the impact until after the project, the focus should be on observing and analyzing early communications and their effects. This aligns with the Cynefin framework's recommendation to probe, sense, and respond, allowing for adaptive management based on feedback and insights gained throughout the project.
Start a Discussions
Project scenario - Get fit with football!
(Note: The companies and people within the scenario are fictional)
Introduction
A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.
Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.
This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.
Scope
The initial scope of the project includes:
The project has been set up with four work streams to deliver this work:
1. Marketing
2. Website
3. Event Village
4. Staff Training
Project Background
The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.
Timeline
An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.

Event Village - Additional information
The aim of the event village is to provide a range of services and activities for anyone attending the football tournament.
The event village will comprise a number of work packages:
1. Event village design
2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities
3. Stalls which will be sold to local businesses to raise funds for the event:
4. A car park for 200 cars.
5. Temporary facilities including changing rooms, toilets and shower facilities.
6. Dismantling of the event village and clean up.
The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.
Using the Project Scenario and Event Village Additional information, answer the following question:
The Event Village Team is holding a workshop to decide how to meet the varied and often conflicting requirements for culturally diverse, healthy and quick food because several days have already been spent trying to establish the way forward. The workshop involves only the Event Village Team without the use of an independent facilitator.
Which reason BEST explains why this workshop is a good application of the 'rich communication' focus area?
Correct : D
Workshops facilitate direct, face-to-face interaction among team members, allowing for richer communication. This informal setting encourages open dialogue, brainstorming, and collaborative problem-solving, which are essential for addressing complex and conflicting requirements effectively.