Question 1

What theme estimates the cost of delivering the project?


Correct : C

The Plans theme in PRINCE2 is responsible for estimating the cost of delivering the project. This theme involves the development of plans that outline how, when, and by whom the project's objectives are to be achieved, including the necessary resources and associated costs. Reference: PRINCE2 Foundation official documentation and study materials.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 2

Which is a purpose of the 'directing a project' process?


Correct : A

The purpose of the 'Directing a Project' process in PRINCE2 is for the project board to exercise overall control over the project while delegating day-to-day management of the project stages to the Project Manager. This process includes decision-making on project initiation and continuation, as well as providing overall guidance on policy and standards. Reference: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 3

In which process should the specified quality methods he used to/prove that a product meets its quality criteria?


Correct : A

The 'Managing Product Delivery' process in PRINCE2 is where the specified quality methods are applied to ensure that a product meets its quality criteria. This process focuses on the acceptance, execution, and delivery of the project's products, ensuring that they are produced to the defined quality standards as part of the overall project delivery.

= PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 4

Which term is defined as the means by which an organization transitions from its current state to the target state?


Correct : A

Change management is defined as the means by which an organization transitions from its current state to the target state. It encompasses all activities involved in managing change, including handling changes to the scope of projects and ensuring that changes are implemented smoothly and sustainably. This involves strategic planning, oversight, and ensuring that changes are accepted and adopted by all stakeholders. Reference: PRINCE2 Foundation training materials and glossary.


Options Selected by Other Users:
Mark Question:

Start a Discussions

Submit Your Answer:
0 / 1500
Question 5

The project management team heeds t document quality antral events, such as testing

According to the guidance for effective quality management, haw should the events be documented?


Correct : D

Quality control events, such as testing, should be documented in the 'Quality Management Approach' according to PRINCE2 guidelines. This document outlines how quality will be managed throughout the project, detailing specific methods and events, including schedules for quality assurance activities and testing, to ensure that products meet their defined quality criteria.

= PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation